Reedbed Project Example
Lancashire, England
There was no access to the site, so a culvert was constructed to access the reedbed site, which was removed when the installation works were complete.
To clean the reed bed out, 4R Group was required to gain a permit for this work.
Compilation of technical drawings, risk assessments and site survey to gain rapid regulatory approval for a temporary bridge to open access to isolated mini reedbed system for vital maintenance works.
Works required
- Site survey
- Regulator liaison
- Compilation of mapping, risk assessments and operational methodology to safely propose the construction, deconstruction and use of a temporary bridge over a protected waterway.
For the duration of the work, we had to look at installing a filtration system to bypass the reedbed.